I-15/Duncan Canyon Road Interchange

Description: In Fontana at Duncan Canyon Road. Construct interchange.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City Fontana
Zip Code 92335
 
Senate District
32
Assembly District 62
Congressional District 43
 
Caltrans District
08
 
 
County/State Route San Bernardino 15
Postmile Begin/End 9.8 11.9
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  1322    1,332  
Lane Miles Added (HOV)      0  
Lane Miles Added (Mixed)      0  
Peak Period Time Savings (minutes)  24610    24,610  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Fontana Kevin Ryan (909)350-6655   kryan@fontana.org
Design (PS&E) Phase
City of Fontana Kevin Ryan (909)350-6655   kryan@fontana.org
Right of Way Phase
City of Fontana Kevin Ryan (909)350-6655   kryan@fontana.org
Construction Phase
City of Fontana Kevin Ryan (909)350-6655   kryan@fontana.org
 
Corridor System Management Plan
City of Fontana Kevin Ryan (909)350-6655   kryan@fontana.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$12,000 $0 $12,000
SLPP
$1,972 $0 $1,972
Non-bond Funding
Local**
$21,302 $0 $21,302
Non Budgeted ETC
$0 $0 $0
 
Total**** $35,274 $0 $35,274

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,020 $0 $1,020 $1,020
Design(PS&E)
$2,500 $0 $2,500 $3,518
Right of Way
$2,800 $0 $2,800 $1,513
Construction
$28,954 $0 $28,954 $28,865
 
Total* $35,274 $0 $35,274 $34,916

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
01/28/2008 

12/03/2009 
100  09/01/2007 

11/03/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

07/05/2012 
100  11/01/2008 

07/02/2012 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100  09/01/2009 

07/02/2012 


Begin Construction Phase

End Construction Phase
 

 
 

 
08/14/2012 

11/30/2016 
100  10/01/2012 

06/30/2017 
-2 

-7 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

11/30/2018 
100   

12/30/2021 


-38 
Corridor System Management Plan
Adoption Date        
Implementation Date        
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 1322 1,332
Lane Miles Added (HOV) 0
Lane Miles Added (Mixed) 0
Peak Period Time Savings (minutes) 24610 24,610

Bond Funding Cost
Adopted:
$13,972,000
Current Approved:
$12,000,000
Actual Expenditures:
$12,000,000

 

Status as of December 31, 2023.